Cleveland Massillon Road Improvement Project

  1. Cleveland-Massillon Pre-Construction Meeting Held

    A Pre-Construction meeting was held on Tuesday June 23 with the selected contractor, TriMor Corp. Representatives from Ohio Dept. of Transportation (ODOT), Summit County, Copley Twp., the inspection firm, and utilities for the project were in attendance. Read on...
  2. Construction Bids

    Bids were received on Friday May 8, 2020. After review, TriMor Corporation was the lowest and most responsive bid at $8,133,955.56. The bid approval from City Council will be presented at the May 18, 2020 Council Meeting. Read on...
  3. Update to Cleveland Massillon Utility Work

    Dominion East Ohio will be finished this week. Ohio Edison is at the intersection of Elgin Drive and Cleveland Massillon Road for two weeks. Summit County D.S.S.S. project is restored from Cleveland Massillon road to the east.
  4. Utility Relocation Continues

    Ohio Edison pole relocation has begun. Also, the Federal Highway Commission has approved the project and bidding will begin soon.
  5. Sewer Line Work

    Sewer line work at Rothrock Road will be crossing Cleveland-Massillon Road Monday March 2nd and Tuesday March 3rd between 10:00 PM and 6:00 AM. Expect delays.
  6. Work Scheduled for Week of February 24, 2020

    Dominion East Ohio Gas should be finishing up work in the right of way this week. Due to the work being done by Dominion, trees along the golf course property were cut down to facilitate the new gas lines. Read on...
  7. Plans, Specifications and Estimates

    On January 31, 2020, The Local Let Plans, Specifications and Estimates package was sent to ODOT for final review. Dominion is placing materials and will start construction this week.
  8. Work Scheduled for Week of February 3rd

  9. December 23, 2019

    We are down to the final 2 acquisition cases. Read on...
  10. November 18, 2019

    Utility move along Cleveland-Massillon Road is proceeding. FairlawnGig has been moved. Read on...
  11. Utility Relocation Work To Be Done on Cleveland-Massillon Rd.

    Beginning Monday October 7, 2019, construction relating to utility relocation will begin on Cleveland Massillon Road. Read on...
  12. August 26, 2019 Update

    We currently have nine parcels that have been successfully closed for the project.
  13. May 20, 2019

  14. May 13, 2019

  15. April 22, 2019

  16. April 8, 2019

  17. March 25, 2019

    All land owners have been contacted for right of way acquisition. Appraisals are in the process of being submitted.
  18. February 22, 2019

    Right of Way Acquisition phase of the Cleveland Massillon Road Widening Project has begun.