Cleveland Massillon Road Improvement Project

  1. 9-25-20 Cleveland Massillon Road Construction Update

    Please remember that Cleveland Massillon Road is closed. Obey all traffic control devices and follow posted detours. Read on...
  2. 9-24-20 Cleveland Massillon Road Construction Update

    Please remember that Cleveland-Massillon Road is closed. Obey all traffic control devices and follow posted detours. Read on...
  3. 9-23-20 Cleveland-Massillon Road Update

    Cleveland Massillon Road is closed. Please obey all signage and follow the posted detours. Read on...
  4. 9-22-20 Cleveland Massillon Road Update

    Please remember that Cleveland Massillon Road is closed. Obey all signage and posted detours. Read on...
  5. 9-21-20 Cleveland Massillon Road Update

    Please remember that Cleveland Massillon Road is closed. Obey signage and follow the posted detours. Read on...
  6. 9-18-20 Cleveland Massillon Road Update

    Below are pictures and descriptions of the work being performed. Please remember that the road is closed and to follow posted detours. Read on...
  7. Cleveland Massillon Road 9-16-20 Update

    See below for pictures and descriptions of work being performed. Please remember that the road is closed and to follow posted detours. Read on...
  8. Cleveland-Massillon Road Closed September 14, 2020

    Cleveland-Massillon Road is officially closed for 45 days as of Monday, September 14, 2020. Please follow posted detours. Read on...
  9. Tree Trimming and Removal Starting 9-11-20

    TriMor Construction has begun tree trimming and removal for the Cleveland Massillon Road Project. Delays are expected and it is suggested that motorist use an alternate route.
  10. 9-11-20 Work Continues

    Frontier will continue with their fiber move this weekend (9/12 - 9/13). Expect delays. Read on...
  11. 9/10/20 - Construction Starts on Cleveland-Massillon Road

    Construction began on September 9th on the extension of the golf cart tunnel. Read on...
  12. 9/10/20 - Expect Delays On Cleveland-Massillon Road

    Due to Frontier moving their fiber lines, delays are expected on Cleveland-Massillon Road. Please watch for flaggers.
  13. Cleveland Massillon Road Construction and Closure

    Cleveland Massillon Road construction will begin on September 8, 2020 with mobilization and maintenance of traffic set up. Read on...
  14. Cleveland-Massillon Pre-Construction Meeting Held

    A Pre-Construction meeting was held on Tuesday June 23 with the selected contractor, TriMor Corp. Representatives from Ohio Dept. of Transportation (ODOT), Summit County, Copley Twp., the inspection firm, and utilities for the project were in attendance. Read on...
  15. Construction Bids

    Bids were received on Friday May 8, 2020. After review, TriMor Corporation was the lowest and most responsive bid at $8,133,955.56. The bid approval from City Council will be presented at the May 18, 2020 Council Meeting. Read on...
  16. Update to Cleveland Massillon Utility Work

    Dominion East Ohio will be finished this week. Ohio Edison is at the intersection of Elgin Drive and Cleveland Massillon Road for two weeks. Summit County D.S.S.S. project is restored from Cleveland Massillon road to the east.
  17. Utility Relocation Continues

    Ohio Edison pole relocation has begun. Also, the Federal Highway Commission has approved the project and bidding will begin soon.
  18. Sewer Line Work

    Sewer line work at Rothrock Road will be crossing Cleveland-Massillon Road Monday March 2nd and Tuesday March 3rd between 10:00 PM and 6:00 AM. Expect delays.
  19. Work Scheduled for Week of February 24, 2020

    Dominion East Ohio Gas should be finishing up work in the right of way this week. Due to the work being done by Dominion, trees along the golf course property were cut down to facilitate the new gas lines. Read on...
  20. Plans, Specifications and Estimates

    On January 31, 2020, The Local Let Plans, Specifications and Estimates package was sent to ODOT for final review. Dominion is placing materials and will start construction this week.
  21. Work Scheduled for Week of February 3rd

  22. December 23, 2019

    We are down to the final 2 acquisition cases. Read on...
  23. November 18, 2019

    Utility move along Cleveland-Massillon Road is proceeding. FairlawnGig has been moved. Read on...
  24. Utility Relocation Work To Be Done on Cleveland-Massillon Rd.

    Beginning Monday October 7, 2019, construction relating to utility relocation will begin on Cleveland Massillon Road. Read on...
  25. August 26, 2019 Update

    We currently have nine parcels that have been successfully closed for the project.
  26. May 20, 2019

  27. May 13, 2019

  28. April 22, 2019

  29. April 8, 2019

  30. March 25, 2019

    All land owners have been contacted for right of way acquisition. Appraisals are in the process of being submitted.
  31. February 22, 2019

    Right of Way Acquisition phase of the Cleveland Massillon Road Widening Project has begun.
View All

Documents